Infocomm international audiovisual systems performance verification checklist -- copyright 2013 infocomm international

Template Information

Audiovisual systems performance verification checklist

Category: general

Template Questions

  • All audio performance tests are made from all electronic system inputs (first physical output of sour
  • Audio Performance
  • Verify that the audio outputs of a multi-channel loudspeaker system are signed correctly with regards
  • Verify that phantom power is provided at the correct voltage and correct locations as defined in the
  • Verify that loudspeaker zones are wired as defined in the project documentation.
  • Verify that all loudspeaker circuits have the correct impedance as defined in the project documentati
  • Verify that audio signal is being distributed accordingly through the system as defined in the projec
  • Verify that all DSP – based products have been programmed as defined in the project documentation and
  • Verify that any required meeting or operational change of the installed sound system(s) are in accord
  • Verify that the background acoustic noise levels within audiovisual spaces or within the required lim
  • Verify that all devices that are part of the assistive listening system have been tested as a complet
  • Verify calibration of permanent audio system inputs so there is minimal difference between any input
  • Verify that audio systems capable of performing above normal operating levels without distortion, as
  • Verify proper alignment, set up, and placement of microphones in the system as defined in the project
  • Verify calibration of microphone so there is microphone input level alignment as defined in the proje
  • Verify that speech reinforcement system is operating without feedback and audio levels as defined in
  • Verify the system with conference capability shall perform at normal operating levels in the full-dup
  • Verify that loudspeakers are placed and aimed as defined in the project documentation.
  • Verify that all loudspeaker time alignment is configured as defined in the project documentation.
  • Verify that all loudspeakers are tested to ensure they all have correct polarity as defined in the pr
  • Measure the impedance of all loudspeaker circuits and compare the results with values defined in the
  • Verify the loudspeaker transformer tap setting is in constant voltage systems as defined in the proje
  • Verify that in a conferencing audio application, the incoming audio level from the far side is checke
  • Verify that the total harmonic distortion of the installed audio system is less than the level define
  • Verify that the audio level provided by the AV system exceeds the background noise level as to find i
  • Verify that equalizers have been adjusted in accordance with the preferred acoustic response curves a
  • Verify that the electronic frequency response of the speech reinforcement system meets or exceeds tha
  • Verify that the electronic frequency response of the audio playback system meets Or exceeds to that w
  • Verify that no audible noise caused by improper installation of any equipment provided in completed s
  • Measure latency of the audio system, and verify that latency does not exceed requirements defined in
  • Verify use of audio dynamics, including but not limited to noise compensation, automatic gain control
  • Verify that audio system sound pressure levels and equalization is calibrated as defined in this proj
  • Verify reverberation time and compare to expectations defined in the project documentation.
  • Verify that the audio system provides speech reproduction as defined in the project documentation.
  • Verify the coverage of the audio system in the Listener areas meets the performance requirements as d
  • Verify that all audio routes are tested from endpoint to endpoint via the appropriate midpoints for o
  • All video performance tests are made from all electronic systems inputs (first physical output of sou
  • Video performance
  • Verify that all displayed images do not have pixel failures (bright or dead pixels) that exceed the r
  • Verify that the combined installation of projector and screen provides a displayed image that is corr
  • Verify that all display images are correctly focused have the correct image geometry and are free fro
  • Verify that the combined installation of projector and screen provides a display to viewer that meets
  • Verify that the displays are sized appropriately to the distance relative to the viewer as defined in
  • Verify that all video routes are tested from endpoint to endpoint via the appropriate midpoints for o
  • Verify calibration of all video displays to ensure the display colors uniformly to a common reference
  • Verify that the system should conform to the appropriate viewing category as defined in the project d
  • Verify that the system Displays all resolutions required by project documentation on all displays wit
  • Verified to EDID (Extension Display Identification Data) management plan has been implemented for the
  • Verify that the HDCP (High-Bandwidth Digital Content Protection) management plan has been implemented
  • Inspect camera image quality through the full lens operation. Check Lens for proper operation. Check
  • Audio/Video performance
  • Verify that audio and video signals are being routed to the recording device and that the recording d
  • Verify that audio/video synchronization is maintained to ensure the proper time alignment of signals
  • Verify that the radio frequency and satellite intermediate frequency distribution systems provide all
  • Verify that emergency communication systems properly receive inputs and information from other system
  • Verify that "real-life" sources other than test generations have been tested on the completed system
  • Verify that the video synchronization of the system is performing as defined in the project documenta
  • Cable management, termination, and labeling
  • Verify that all cables are adequately supported throughout their links as defined in the project docu
  • Verify that all cable terminations are made securely and meet the recommendations of the connector an
  • Verify that all patch panels have been labeled as defined in the project documentation. Verify that a
  • Verify that all patch panels have been correctly wired and configured as defined in the project docum
  • Verify that all AV equipment power cables are managed as defined in the project documentation, verify
  • Verify that all connectors are correctly keyed, seeded, and latched to respective connection points a
  • Verify the cables are dressed to ensure that all rack and site cables are installed to provide servic
  • Verify all AV connector plate input and output labeling as defined in the project documentation.
  • Verify that all cables are identified by unique ID as defined in the project documentation. Verify th
  • Verify that AV connector plates have consistent labeling throughout the project as defined in the pro
  • Verify that were appropriate, cable ties are used to secure the cables and that the correct type of c
  • Verify that both site and rack cables have appropriate separation according to signal type and level
  • Verify that sufficient cabling is available so the device can be placed in a serviceable location as
  • Verify that cables are not bent beyond the minimum bend radius as specified in cable datasheet in ord
  • Verify that all cable terminations have been completed and adequately supported so as to minimize wei
  • Purify the cables were only bundled together when their construction, Signal type,, and signal level
  • Verify that all cabling is of the correct type and routed correctly from point-to-point as defined in
  • Control performance
  • Verified any required response of the installed audiovisual system in the event of life safety or sim
  • Verify that mobile devices that are to be supported are integrated and operating as defined in the pr
  • Verify that all control communications are tested from endpoint to endpoint via the appropriate midpo
  • Verify that the look and feel of the control system is consistent with requirements as defined in the
  • Verify that all macro functions executed by the control system conform to requirements as defined in
  • Verify that AV control system interfaces to and control systems provided by others and conforms to re
  • Electrical
  • Verify that all AV equipment is powered from the designated power circuit and outlet as defined in th
  • Verify that all electrical sub distribution systems provided by the AV contractor in equipment racks,
  • Verify that the sources of mains voltage AC power to be used for the supply of audiovisual equipment
  • Verify that all elements of the audiovisual system are correctly bonded to an electrical ground earth
  • Verify that the power sequencing of devices is correct per the project documentation.
  • Verify that all DC power devices are receiving the proper voltage and current for normal operation. W
  • Verify that the uninterruptible power supply (UPS) is performing to the specifications as defined in
  • Verify the A/V systems for normal operation on the resumption of power following a hard electrical po
  • Verify power monitoring equipment is working and reporting as defined in the project documentation. P
  • Information technology
  • Verify that the network for audio, video, and control is it suitable to apology to support the servic
  • Verify that any required telephony connections to the AV system are in place and connectivity is veri
  • Verify any connections to IP-based unified communications applications that will interface with the A
  • Verify that POE (Power over ethernet) devices are supplied with correct power required for device nor
  • Verifying document that all network connected equipment has the correct IP address, subnet mask, host
  • Verify that the correct and valid wireless network configuration (e.g. channel number, SSID, TX power
  • Verify that the required network bandwidth is available to control, audio, video, and data as part of
  • Verify that the required quality of service (QOS) is in place for audio, video, and data as part of e
  • Verify the network can provide the required operational performance to carry control, audio, video, a
  • Verified the shared or dedicated network is secure as defined in the project documentation and access
  • Verified the content delivery network is in place and provides the required connectivity, bandwidth a
  • Verified the audiovisual and control systems have been integrated and fully configured with headend s
  • Verify that the wireless network is protected in accordance with the clients information security pol
  • Verify that the digital enhanced cordless Telephony the (DECT)/unlicensed personal communication serv
  • Verify the remote access to AV and IT systems are configured as defined in the project documentation.
  • Verify that all systems authentication credentials are configured correctly. Any temporary credential
  • Verify that remote management tools such as virtual touch panels, internal web applications, or manuf
  • Verify that enterprise management tools such as central monitoring client/server or web-based applica
  • Operational
  • Verify that a battery management plan has been completed and supplied in the project documentation pa
  • Verify that any system content that will be used in initial operations has been supplied to the owner
  • Verify there is a plan for managing the content to be delivered by the A/V systems including the mean
  • Verify that all control programming code, DSP configuration files, and any other associated software
  • Physical environment
  • Verify the HVAC system has been tested and balanced prior to completing checklist item AP – 122 and A
  • Verify that installed backing, blocking and framing meets project documentation requirements and indu
  • Verify that installed floor, wall and ceiling boxes meet project documentation and regulatory authori
  • Verify the device enclosures are suitable to house the device intended and that all necessary environ
  • Verify that human factor elements for audience and system users are installed and configured as defin
  • Verify configuration and compatibility for structural accommodations and all mounting hardware based
  • Verify that the divisible spaces provide the functionality specified as defined in the project docume
  • Verify that the physical environment is suitable for the intended A/V systems in relation to all sour
  • Verify that the lighting systems are suitable for the intended video and control systems for each typ
  • Verify that the area is clean and dust free and suitable for equipment installation and that no furth
  • Verify that all elements of the AV system are free of damage.
  • Verify AV equipment, furniture, fixtures, and accessories against the project documentation.
  • Verify the HVAC system has begun continuous operations in advance of equipment operations.
  • Verify that all systems are accessible in accordance with regulatory requirements.
  • Verify that the elements, including but not limited to spatial requirements and building services req
  • Physical installation
  • Verify that installed containment/conduit capacity and routes meet project documentation requirements
  • Verify that AV equipment is installed at the location and/or in the rack or enclosure defined in the
  • Verify that all AV equipment has been labeled in accordance with the requirements of the project docu
  • Verify that the AV rack thermal gradient has been inspected and all equipment is operating within man
  • Verify that all AV equipment has been installed, aligned, or angled correctly as defined in the proje
  • Verify that all components installed in AV equipment racks are free from dirt, dust, water, or any ot
  • Verify that all optical components, such as lenses and mirrors, or free from dirt, dust, damage, or m
  • Verify that any equipment that may be considered "portable" and/or otherwise not specifically incorpo
  • Verify that installed items with user facing controls that are not intended for end-user access have
  • Verify that equipment in the project is secured per the project documentation. All security systems,
  • Verify that all elements of the AV system are free from loss, damage, or tampering.
  • Verify that there is uniform handling of items that may have been prepackaged with primary system equ
  • Serviceability
  • Verify that all input and output panels are accessible and meet all requirements for user access and
  • All equipment shall be accessible and capable of being maintained, serviced, cleaned, or adjusted as
  • Verify rack placement and use for physical stability in accordance with the project documentation and
  • Verify any panels that have been installed to provide access to any type of AV equipment or properly
  • Wireless
  • Verify that the environment is suitable for the required wireless services (RF and IR) to provide aud
  • Verify that the operation of wireless audio systems (RF and IR) is as defined in the project document
  • Verify that the operation of wireless video systems (RF and IR) is as defined in the project document
  • Verify that the operation of wireless control systems (RF and IR) is as defined in the project docume
  • Documentation
  • Verify the complete set of accurate as built drawings indicating all AV devices, AV device locations,
  • Verify that any integrators testing requirements have been performed and approved as defined in the p
  • Verify that any third-party testing requirements have been performed and approved as defined in the p
  • Verify that a final acceptance of the project has been issued by the owner or owners representative,
  • Verify that a conditional acceptance of the project has been issued by the owner or owners representa
  • Verified all equipment is in shop or on site as defined in the project documentation. List all equipm
  • Verify that any owners testing requirements defined in the project documentation have been performed
  • Verify that any Manufacturers testing requirements defined in the project documentation have been per
  • Verify that any General contractors testing requirements defined in the project documentation have be
  • Verify that any Consultants testing requirements defined in the project documentation have been perfo
  • Verify that the usage and ownership rights have been assigned as defined in the project documentation
  • Verify that the correct and valid wireless frequency licensing permits have been obtained to ensure l
  • Verify that the video system test report has been completed and issued to the proper entity as define
  • Verify that the Audio system test report has been completed and issued to the proper entity as define
  • Verify that the Control system test report has been completed and issued to the proper entity as defi
  • Verify that samples of all equipment to be used as defined in the project documentation have been sub
  • Where samples of products have been required for approval, verify that the products that are delivere
  • Verify that manufacturer's users manuals are delivered to the owner in a format defined in the projec
  • Verify that the manufacturer's product warranty cards are provided to the owner. The owner shall be n
  • Verify that the final commissioning report has been completed, issued to the proper entity, and accep
  • Verify that a complete set of as built system documentation has been provided as defined in the proje