Kalkreuth roofing & sheet metal, inc. checklist
Roofing safety inspection
此表单包含什么?
此表单包含 15 个部分:
Access / Egress
- Portable Ladders
- Fixed Ladders
- Stepladders
- Stairs
- Other
Electrical Safety
- GFCI utilized at all times
- Cords and tools in good condition. Damaged cords / tools tagged out of service or rendered inoperable
- All cords protected from damage (not exposed to vehicular traffic or crushing damage from doors or windows, etc.)
- All ladders and equipment at least 10' from electrical lines
Fall Protection
- No fall from height exposures present. Typically ground work, high parapet walls (39" or greater), or similar structure is present which eliminates fall from height exposure.
- Warning Line Systems
- Guardrails System
- Safety Monitoring System
- Personal Fall Arrest Systems
- Skylight and hole protection
- Hoist area fall protection
- Other
Add media
Fire Prevention
- Extinguishers in place, charged and in work area. Clear of obstruction. No more than 100' from employees, no more than 50' from flammables
- No smoking near flammables
- Proper flammable safety cans in use
General Safety
- First aid kits available onsite
- SDS available onsite for all chemicals, chemicals properly labelled
- Weekly tool box talks conducted
- General housekeeping efforts kept up
- All materials and debris secured daily. Public protected from falling / flying objects
- General precautions taken to protect property from damages
- Intakes covered or turned off when chemicals used
Hand and Power Tools
- All hand and power tools in good repair. Damaged equipment tagged out of service or rendered inoperable
- All power tools have proper machine guards in place
- Hand tools used for the task they are designed for. No prying items with a utility knife
- Utility knife blades kept sharp, cuts made away from body. Retracted or fully sheathed when not in use
Material Handling
- Proper lifting techniques observed. Team lifts or mechanical equipment used when lifting heavy objects
- Material handling equipment in good condition
- Debris removed of promptly and safely. Chute provided when over 20'.
Personal Protective Equipment
- Eye protection worn when hazard exits and per policy
- Hard hats worn when hazard exits and per policy
- Proper gloves worn when handling tear off debris, when handling sharp metal, and when handling chemicals requiring glove usage
- Proper work attire worn (boots, pants, sleeved shirts, long sleeve shirts if handling hot asphalt)
Scaffolding
- Supported Scaffolding
- Aerial Lifts
- Other
Specific Roof Systems Hazards
- Modified Bitumen - Torch Applied System (if not checked than N/A)
- BUR - Kettle Safety (if not checked than N/A)
- Other
Jobsite Grading
- Acceptable: Jobsites which have no serious violations of federal requirements, or safety policies and have recognizable hazards controlled at the time of the inspection.Needs Improvement: Jobsites in which violations occurred which may be serious in nature but the inspector does not believe them to be done intentionally or egregiously.Unacceptable: Jobs in which egregious safety violations exist and are to believe to have been known by those involved.
Corrective Actions taken onsite to correct noted deficiencies:
On site representative
Auditor's signature