Fire pump room checklist
Inspection of fire installation pumps
What does this form include?
This form contains 6 sections:
Installations 1-10
- Are all the Installations from 1-10 within acceptable levels (1200Kpa-1600Kpa)IF NOT:Include current Pressure Reading, Installation No. & include a Photo of the gauge(s) as evidence of reading in the comments section below
Pump Installations:
- Main Sprinkler Pump:Is the Installation within acceptable levels (1000Kpa-1300Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Sprinkler Servicing Pumps:Is the Installation within acceptable levels (900Kpa-12000Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Hydrant Main Pump:Is the Installation within acceptable levels (1000Kpa-1200Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Hydrant Servicing Pumps:Is the Installation within acceptable levels (900Kpa-1200Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Diesel Electric Pump:Is the Installation within acceptable levels (1100Kpa-1400Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Diesel Jacking Pump:Is the Installation within acceptable levels (900Kpa-1200Kpa)IF NOT:Include current Pressure Reading & include a Photo of the gauge as evidence of reading
- Has any OH&S hazards been detected within the Fire Pump Room(If the answer is yes, please elaborate further and attach a photo of the hazard
Any additional comments that you wish to add, please add them here
Time Audit completed Date
Add signature