Concrete pre pour checklist
Check sheets
What does this form include?
This form contains 14 sections:
Nature and Location of work to be inspected
SECTION 1 - NOTICE OF CONCRETE OPERATIONS
- Are you in possession of the most current set of drawings?
- Are you in possession of the approved submittal and correct mix design?
Time available for inspection Date
REINFORCEMENT and INSTALLATION
- Blinding/Formation level checked befor installation?
- Cover to concrete, Spacers & Chairs as per the spec & Drawing?
- Is all reinforcing installed clean and free of debris? (top, Bottom & Verts)
- Dimensions of prefab'd cages , Location Checked befor installing?
- Rebar in its respective position according to the layout & Snap Tieed?
- Have all the shear links installed ?
- Bar size, spacing, & Lap lengths Fixed as per drawing's? (top, Bottom & Verts)
- Fixer forman available on the location at time of inspection?
Date & Time steel Inspected Date
Forman Fixture
Formwork, Falsework & etc
- LIne & Levels are setout at the correct location per the current set of drawings?
- slab penetrations / Service pipes , Built in Items are installed at the correct location per the current set of drawings?
- Joint details including waterbars installed per specification?
- Cover to Reiforcement checked before Formwork?
- Is the proper form release agent as defined in the specifications and approved submittals, on site in the work area and readily available in quantity necessary to cover the forms for the area of slab being placed?
- Temporary work design approved and Permit signed off ?
Temporary work coordinator
Cube Reference:-
HCPL Foreman
HCPL Engineer
We trust this meets with your approval and ask you to sign, copy and return this form to our site office.
- The above works are approved by BOUYGUES for concreting
Date & Time: Date
Signed for BOUYGUES