Idi ceiling framing quality control checklist
Ceiling framing qaqc
ماذا يتضمن هذا النموذج؟
يتضمن هذا النموذج 4 أقسام:
Confirm for updated drawings, RFI's, plans & specs
- Confirm for updated drawings, RFI's, plans & specs
- Confirm MEP overhead complete & sign off prior to ceiling framing
- Confirm MEP rough opening layout complete (lights, grilles, diffusers)
- Confirm MEP access door
- Confirm fire-stop or sound caulk at head of wall (if required)
- Confirm fire-taping and sound caulking of wall above ceiling (if required)
- Confirm studs/drywall grid are installed per plans/specs
- Confirm backing installed at items hung from ceilings
- Confirm ceiling & soffit heights per plans/specs
- Confirm cleanup of our cartons and scrap materials
- Inspect and walk the site with the G.C. Superintendent
Comments
Sign Off
I.D.I. QAQC Inspector