  • Verification items within this category verify the audio system’s performance, stability, and conform
  • Audio Performance
  • Verify that any required muting or operational change of the installed sound system(s) has been made
  • Verify that loudspeaker zones are wired as defined in the project documentation.
  • Verify calibration of permanent audio system inputs such that the difference between any input signal
  • Verify that no audible noise caused by improper installation of any equipment provided in completed s
  • Verify that all audio routes are tested from endpoint to endpoint via the appropriate midpoint(s) for
  • Verify reverberation time meets the requirement defined in the project documentation. This verificati
  • Verify that all DSP-based products have been programmed as defined in the project documentation.
  • Verify that loudspeakers are placed and aimed as defined in the project documentation.
  • Verify that all loudspeakers have correct polarity as defined in the project documentation.
  • Verify that loudspeaker time alignment performs as defined in the project documentation. This verific
  • Verify that phantom power is provided at the correct voltage and correct locations as defined in the
  • Verify the loudspeaker transformer tap setting in constant voltage systems is as defined in the proje
  • Verify that the background acoustic noise levels within audiovisual spaces are within the required li
  • Verify that all devices that are part of the assistive listening system have been tested as a complet
  • Verify that coverage of the audio systems in listener areas meets the performance requirements as def
  • Verify use of audio dynamics, including but not limited to noise compensation, automatic gain control
  • Verify that the audio level provided by the installed audio system exceeds the background noise level
  • Verify that the electronic frequency response of the audio system is as defined in the project docume
  • Verify that the audio system equalization is in accordance with the acoustic response curves as defin
  • Verify that audio system latency meets requirements defined in the project documentation. This verifi
  • Verify that the audio system provides speech reproduction (intelligibility) as defined in the project
  • Verify that the total harmonic distortion of the installed audio system is as defined in the project
  • Verify that in a conferencing audio application, the incoming and outgoing audio levels are checked a
  • Verify that a system with conferencing capability performs at nominal operating levels in a full dupl
  • Verify that all loudspeaker circuits have the correct impedance as defined in the project documentati
  • Verify proper alignment and placement of microphones in the system as defined in the project document
  • Verify that the speech reinforcement system is operating without feedback and at audio levels as defi
  • Verify calibration of microphone inputs so that the difference between any input signal level after t
  • Verify that the audio outputs of a multi-channel loudspeaker system are assigned correctly to designa
  • Verify that audio system sound-pressure levels and equalization are adjusted to the level of sound ma
  • Verify that the audio system is capable of performing above nominal operating levels without distorti
  • Verify audio system electrical signal-to-noise ratio meets the minimum levels defined in the project
  • Verification items within this category verify the video system’s performance, stability, and conform
  • Video performance
  • Verify that the EDID (Extended Display Identification Data) management plan has been implemented as d
  • Verify that the HDCP (High-bandwidth Digital Content Protection) management plan has been implemented
  • Verify that the combined installation of projector and screen provides a displayed image that is corr
  • Verify that all displayed images do not have pixel failures (bright or dead pixels) that exceed the r
  • Verify that all displayed images are correctly focused, have the correct image geometry and are free
  • Verify that the components of the displayed image system(s) (projection or direct-view) perform(s) as
  • Verify calibration of all video displays to ensure they display colors uniformly to a common referenc
  • Verify that the system(s) accurately displays all resolutions required by project documentation on al
  • Verify that the combined installation of projector and screen provides a display to the viewer that m
  • Verify that the system conforms to the appropriate viewing category as defined in the project documen
  • Verify that all video routes are tested from endpoint to endpoint via the appropriate midpoint(s) for
  • Verify that cameras, lenses, and pan/tilt systems operate as defined in the project documentation. In
  • Verification items within this category verify linked audio and video system elements that cannot be
  • Audio/Video performance
  • Verify that emergency communications systems properly receive inputs and information from other syste
  • Verify that the video synchronization of the system is performing as defined in the project documenta
  • Verify that audio and video signals are being routed to the recording device(s) and that the recordin
  • Verify that audio/video synchronization is maintained to ensure the proper time alignment of signals
  • Verify that the radio frequency and satellite intermediate frequency distribution systems provide all
  • Verify that the signal produced by a source typical of what will be used in normal operation of the s
  • Verification items within this category verify the workmanship for installation and management of all
  • Cable management, termination, and labeling
  • Verify that cables are not bent beyond their minimum bend radius as specified in cable data sheet in
  • Verify that all AV connector plate inputs and outputs are labeled as defined in the project documenta
  • Verify that all AV connectors are correctly keyed, seated, and latched to respective connection point
  • Verify that all AV cable terminations are made securely and meet the recommendations of the connector
  • Verify that all AV equipment power cables are managed as defined in the project documentation. Verify
  • Verify that all AV system cables are identified by a unique ID as defined in the project documentatio
  • Verify that both site and rack cables have appropriate separation according to signal type and level
  • Verify that all cables are supported throughout their lengths as defined in the project documentation
  • Verify that, where appropriate, cable ties are used to secure the cables, are correctly tensioned, an
  • Verify that cables are only bundled together when their construction, signal type, and signal level a
  • Verify that cables are dressed to ensure that all rack and site cables are installed to provide servi
  • Verify that all patch panels have been correctly wired and configured as defined in the project docum
  • Verify that all patch panels have been labeled as defined in the project documentation. Verify that a
  • Verify that all cable terminations have been completed and adequately supported to minimize stress on
  • Verify that AV connector plates have consistent labeling throughout the project as defined in the pro
  • Verify that all cabling is the correct type and routed correctly from point to point as defined in th
  • Verify that sufficient cabling is available so the device can be placed in a serviceable location as
  • Verification items within this category verify the control system’s performance, usability, stability
  • Control performance
  • Verify that all control communications are tested from endpoint to endpoint via the appropriate midpo
  • Verify that AV control system interfaces to and from control systems provided by others conform to re
  • Verify that mobile devices that are to be supported are integrated and operating as defined in the pr
  • Verify that any required response of the installed audiovisual system(s) in the event of a life safet
  • Verify that all time-dependent or automated functions executed by the control system conform to requi
  • Verify that the control system is implemented in a manner consistent with the requirements as defined
  • Verify that the control system provides the user response time and maximum latency defined in the pro
  • Verification items within this category verify that the system’s project-specific record documentatio
  • System and Record Documentation
  • Verify that all equipment has been delivered as defined in the project documentation.
  • Verify that samples of all equipment to be used as defined in the project documentation have been sub
  • Where samples of products have been required for approval, verify that the products that are delivere
  • Verify that the correct and valid wireless frequency licensing permits have been obtained for legal o
  • Verify that any consultant’s testing requirements defined in the project documentation have been perf
  • Verify that any general contractor’s testing requirements defined in the project documentation have b
  • Verify that any integrator’s testing requirements have been performed and approved as defined in the
  • Verify that any manufacturer’s testing requirements defined in the project documentation have been pe
  • Verify that any owner’s testing requirements defined in the project documentation have been performed
  • Verify that any third-party testing requirements have been performed and approved as defined in the p
  • Verify that a conditional acceptance of the project has been issued by the owner or owner’s represent
  • Verify that a complete set of accurate as-built drawings indicating all AV devices, AV device locatio
  • Verify that the audio system test report has been completed and issued as defined in the project docu
  • Verify that the control system test report has been completed and issued as defined in the project do
  • Verify that the final commissioning report has been completed, issued to the proper entity, and accep
  • Verify that a complete set of as-built system documentation has been provided as defined in the proje
  • Verify that the usage and ownership rights have been assigned as defined in the project documentation
  • Verify that manufacturer’s user manuals are delivered to the owner in a format defined in the project
  • Verify that the video system test report has been completed and issued as defined in the project docu
  • Verify that all warranties are activated and that all warranty details have been passed to the owner
  • Verify that a final acceptance of the project has been issued by the owner or owner’s representative,
  • Verification items within this category verify the system’s interaction with mains voltage distributi
  • Electrical
  • Verify that all AV equipment is powered from the designated power circuit and outlet as defined in th
  • Verify that all elements of the AV system are correctly bonded to an electrical ground/earth in accor
  • Verify that all electrical sub-distribution systems provided by the AV contractor in equipment racks,
  • Verify that the sources of mains voltage AC power to be used for the supply of AV equipment are corre
  • Verify that the power sequencing of devices is correct as defined in the project documentation.
  • Verify that the uninterruptible power supply (UPS) is performing to the specifications as defined in
  • Verify that all DC powered devices are receiving the proper voltage and current for normal operation.
  • Verify that the AV systems resume normal operation on the restoration of power following a hard elect
  • Verify power-monitoring equipment is working and reporting as defined in the project documentation. P
  • Verification items within this category verify the Information Technology elements of the system perf
  • Information Technology
  • Verify that the content delivery network (e.g., digital signage) is in place and provides the require
  • Verify that the wireless network is protected in accordance with the client/owner’s information secur
  • Verify that the required network bandwidth is available for control, audio, video, and data as part o
  • Verify that the required Quality of Service (QoS) is in place for audio, video, and data as part of e
  • Verify that the shared or dedicated network is secure as defined in the project documentation and acc
  • Verify that any required telephony connections to the AV system are in place and connectivity is veri
  • Verify that any connections to IT-based unified communication applications that will interface with t
  • Verify and document that all network-connected equipment has the correct IP address, subnet mask, hos
  • Verify that the wireless network configuration is correct and valid (e.g., channel no., SSID, TX powe
  • Verify that PoE (Power over Ethernet) devices are supplied with correct power required for normal dev
  • Verify that the network for audio, video, and control is of a suitable topology to support the servic
  • Verify that the audiovisual and control systems have been integrated and have been fully configured w
  • Verify that enterprise management tools such as central monitoring client/server or web-based applica
  • Verify that all systems-authentication credentials are configured correctly. Any temporary credential
  • Verify that the network can provide the required operational performance to carry control, audio, vid
  • Verify that remote access to AV and IT systems are configured as defined in the project documentation
  • Verify that remote management tools such as virtual touch panels, internal web applications, or manuf
  • Verification items within this category verify that operational planning and handover of elements of
  • Operations and Support
  • Verify that all control programming code, DSP configuration files, and any other associated software
  • Verify that a battery management plan has been completed and supplied to the owner in the project doc
  • Verify there is a plan for managing the content to be delivered by the audiovisual systems, including
  • Verify that any owner, vendor, or third-party-produced system content that is required for operations
  • Verification items within this category verify that built elements that interact with a system perfor
  • Physical Environment
  • Verify that the divisible spaces provide the functionality defined in the project documentation.
  • Verify that ergonomics and usability elements for audience and system users are installed and configu
  • Verify that the lighting systems are suitable for each type of application (e.g., video conferencing,
  • Verify that the physical environment is suitable for the intended audiovisual systems in relation to
  • Verify that installed backing, blocking, and framing meets project documentation requirements and ind
  • Verify that the area is clean, free of dust, and suitable for equipment installation and that no furt
  • Verify that the elements (including but not limited to spatial requirements and building services) re
  • Verify that device enclosures accommodate the intended device and that all necessary environmental co
  • Verify AV equipment, furniture, fixtures, and accessories against the project documentation.
  • Verify that installed floor, wall, and ceiling boxes meet project documentation and regulatory author
  • Verify the HVAC system has been tested and balanced prior to completing verification items AP-112 and
  • Verify the HVAC system has begun continuous operations in advance of equipment operations.
  • Verify configuration and compatibility of structural accommodations and all mounting hardware based o
  • Verify that all elements of the AV system are free of damage.
  • Verify that all systems are accessible in accordance with regulatory requirements.
  • Verification items within this category verify that the workmanship for installation of all the equip
  • Physical Installation
  • Verify that installed containment/conduit capacity and routes meet project documentation requirements
  • Verify that the AV rack(s) provides the air flow as required in the project documentation. Verify tha
  • Verify that equipment is secured as defined in the project documentation. Verify that all security sy
  • Verify that all AV equipment has been labeled in accordance with the requirements of the project docu
  • Verify that all AV equipment has been installed, aligned, or angled correctly as defined in the proje
  • Verify that all elements of the AV system are free from loss, damage, or tampering.
  • Verify that AV equipment is installed at the location and/or in the rack or enclosure as defined in t
  • Verify that all components installed in AV equipment racks are free from dirt, dust, water, or any ot
  • Verify that installed items with user-facing controls that are not intended for end-user access have
  • Verify that all optical components, such as lenses and mirrors, are free from dirt, dust, damage, or
  • Verify that all items that are pre-packaged with primary system equipment but have no documented/plan
  • Verify that any equipment that may be considered portable and/or otherwise not specifically incorpora
  • Verification items within this category verify that the system is serviceable in conformance with the
  • Serviceability
  • Verify that any access panels that have been installed to provide access to any type of AV equipment
  • Verify that all equipment is accessible and capable of being maintained, serviced, cleaned, or adjust
  • Verify that all input and output panels are accessible and meet all requirements for user access and
  • Verify rack placement and use for physical stability in accordance with the project documentation and
  • Verification items within this category verify that all aspects of wireless audio, video, and control
  • Wireless
  • Verify that the operation of wireless audio systems (RF and IR) is as defined in the project document
  • Verify that the operation of wireless control systems (RF and IR) is as defined in the project docume
  • Verify that the environment is suitable for the required wireless services (RF and IR) to provide aud
  • Verify that the operation of wireless video systems (RF and IR) is as defined in the project document