Structural steel & metal deck checklist

Template Information

Qc field signoff

Category: general

Template Questions

  • Confirm all leveling nuts and are placed (within footprint of base plate) and at correct elevation.
  • All steel erected per shop drawings.
  • Columns plumbed and structure erected within AISC tolerances.
  • Visual inspection of all TC bolts snapped.
  • Visual inspection of all hex bolts marked for "turn-of-the-nut".
  • Finger-tight connections inspected and verified double-nut or damaged threads.
  • Inspection of all washers and heavy-duty washers at oversized and slotted holes.
  • Confirm all bolt holes are filled.
  • All field welds visually inspected, accepted, and initialed. Document on daily reports.
  • Plumb columns to within AISC tolerances.
  • Snug up leveling nuts and shim plates, torque column anchor bolts, and weld plate washers in place. Pound in/out shim plates projecting outside of baseplate.
  • All deck installed per shop drawings.
  • All closures installed.
  • Deck attachments and side lap fasteners installed per shop drawings.
  • Studs installed per shop drawings.
  • Ceramic ferrules broken.
  • Bent plate installed and welded per shop drawings.
  • Holes in deck foamed and/or closed.
  • All tools, materials, and debris removed from deck.
  • Deck signed off for safety. Safety cable installed/tightened, holes covered/marked etc...
  • Random sample verification of IWF sign-offs above. (10% of all welds and connections).
  • Erection and detailing inspected and signed off by 3rd party inspector.
  • Decking and studs inspected and signed off by 3rd party inspector.
  • All RFI's, FW's, and supplemental info pertaining to this area complete and inspected.