Template Questions

  • Is there a Material Safety Data Sheets attached to the SSSP in relation to the tasks being completed ?
  • Notes
  • Is there adequate site fencing?
  • Is there adequate site signage?
  • Are first aid kits in place & well stocked?
  • Are there adequate toilet facilities sufficient for site Workers?
  • Are toilet areas clean & tidy?
  • Are appropriate fire extinguishers charged & current (Serviced 12 monthly)
  • Are work areas clean & tidy?
  • Are access ways clear? (including stairways)
  • Are materials stacked safely?
  • Have hazardous substances and chemicals been adequately controlled/stored?
  • Have combustable materials and substances been adequately controlled/stored?
  • Have all vertical reinforcing steel bars been capped by client?
  • Are slips & trips hazards controlled?
  • Is Dust controlled?
  • Is Construction Waste being controlled?
  • Is Construction Noise being controlled?
  • Are stepladders set up on firm level gound?
  • Are stepladders in good condition?
  • Are workers using step ladders correctly?
  • Are ladders of industrial standard (complying with AS/NZ 1892.1:1996)?
  • Are Workers using ladders correctly?
  • Are ladders set up on firm level ground?
  • Are ladders secured? (base and/or top)
  • Is ladder set at correct angle? (4 up to 1 out)
  • Are ladders in good condition?
  • Do ladders project 1m above step off point?
  • Are fall hazards controlled?
  • Are fall edges fitted with guardrails/toeboards?
  • Are holes & floor penetrations covered and marked?
  • Are stairways fitted with handrails?
  • Are restraint systems being used in preference to fall arrest systems?
  • Have Employees undertaken training for harness use?
  • Is the fall arrest system suitable for the work requirements?
  • Was all equipment checked prior to use?
  • Are harnesses correctly fitted?
  • Is equipment in serviceable condition?
  • Is there rescue plan in place? (See sssp.)
  • Is EWP set up on firm level ground?
  • Are outriggers fully extended?
  • Has area at base of EWP been isolated/coned ?
  • Is EWP at least 4m from power lines?
  • Are safety harnesses being worn in boom mounted buckets?
  • Has EWP been inspected & certified within last 6 months?
  • Is mobile scaffold suitable for the job?
  • Is mobile scaffold set up on firm level ground?
  • Are wheels locked?
  • Are working levels fully decked & secure?
  • Is access from within the scaffold frame?
  • Are outriggers fitted where required?
  • Has scaffold been erected by Certified Scaffolder?
  • Is scaf-tag/acu-log scaffold register up to date?
  • Are ladders on scaffold secured?
  • Does ladder extend 1m past step off? (or suitable hand holds)
  • Is there suitable access to scaffold platforms?
  • Are work platforms adequate?
  • Are there guardrails / fall protection adequate?
  • Is there an intermediate rail in place?
  • Is a toeboard in place?
  • Is there debris netting in place?
  • Are roof suspension rigs secured against movement?
  • Are Workers connected to independent safety line or other engineered anchor system?
  • Are warning notices and barricades at ground level?
  • Are chemicals stored in proper containers?
  • Has mandatory PPE for site been specified and signage posted?
  • Are hard hats being worn where required?
  • Are safety glasses/goggles being worn where required?
  • Are respirators or masks being worn where required?
  • Is hearing protection being worn where required?
  • Are appropriate gloves being worn where required?
  • Is protective clothing being worn where required?
  • Is high visibility clothing being worn where required?
  • Is safety footwear being worn where required?
  • Are electrical tools and leads visually inspected for faults prior to use?
  • Are electrical leads and tools free from defects and damage?
  • Are electrical tools and leads tagged quarterly?
  • Are protected power outlets being used on site (e.g. lifeguards or RCDs)?
  • Are lifeguard units tagged & tested ?
  • Are electrical tools and leads industrial rated, tagged & tested ?
  • Does temporary festoon lighting have moulded line sockets?
  • Are electrical leads clear of pathways and stairs?
  • Are electrical leads clear of water?
  • Are gas bottles secured in use and/or stored correctly?
  • Do gas sets have flash black arrestors?
  • Is there a Hot Work Procedure/Permit System?
  • Are there welding screens and/or signs in place?
  • Is there an appropriate extinguisher at the work area?
  • Is Asbestos Removal in accordance with DoL Guidelines?
  • Is there a Supervisor with a Certificate of Competence for Restricted Work?
  • Is there an Asbestos Removal Plan on site?
  • Has access to work area been restricted?
  • Has adequate signage been posted at work area?
  • Is there adequate containment of partical drift?
  • Is there adequate air extraction with HEPA filter?
  • Is air monitoring for contamination being performed?
  • Is noise level for operations/site being measured?
  • Is Worker exposure to noise being monitored?
  • Have work operations been arranged to reduce exposure to noise hazards?
  • Has plant and equipment been configured to reduce noise?
  • Are Workers wearing hearing protection on site?
  • Is hearing loss of Workers being moniitored?
  • Is shade cover or screens over work areas where practicable?
  • Are Employees wearing clothing to prevent sun exposure?
  • Is there a sun screen on site of the broad spectrum range?
  • Does the sun screen on site provide a sun protection factor of 30 or more?
  • Are Workers on site applying sun screen to exposed skin areas?
  • Is there a Confined Space Management (CSM) plan on site?
  • Is there a competently trained CSM Supervisor on site?
  • Have all Workers been trained to work in a Confined Space (CS)?
  • Is an Entry Permit System in use to manage CS work?
  • Is a monitoring person stationed outside the CS while work in progress?
  • Have all services associated with CS been disconnected or isolated (lockout tagout)?
  • Does the CSM Plan describe the Emergency Rescue Procedures?
  • Is Emergency Rescue Equipment available at or near the entry?
  • Is emergency breathing apparatus available at or near the entry?
  • Before entry to CS is atmospheric testing carried out?
  • During work in CS is atmospheric testing carried out?
  • Is there a Demolition plan that complies best practice standard?
  • Is there an Engineer's Report/advice?
  • Is there a Demolition Supervisor on site?
  • Is there site security fencing?
  • Is there signage for demolition activities?
  • Is there gantry/overhead protection for the public?
  • Have all building services been disconnected?
  • Are Concrete Workers trained and competent?
  • Are Cement Workers protected from contact with wet cement?
  • Is concrete pump boom area isolated from Workers being underneath?
  • Is clean water on site readily available?
  • Have underground services been located? (plans, service location)
  • Are excavations battered, braced or supported? (trenches >1.5m deep)
  • Is there adequate shoring, trenchshields, sheetpiles before entry into excavations?
  • Is their edge protection to prevent falls?
  • Is there safe ladder access to excavation?
  • Does job method avoid work in unsupported trenches?
  • Is materials & spoil stored to prevent edge collapse? (600mm)
  • Are vehicles & plant at distance to prevent collapse?
  • Is a "stop block" used for tipping vehicles?
  • Is there a temporary Traffic Management Plan (TMP) on site?
  • Has the TMP been approved by the Road Controlling Authority?
  • Are the Traffice Mangagement (TM) measures and signage set up as per the TMP?
  • Is TM supervised by a qualified (STMS)?
  • Is there a Traffice Controller (TC ) on site?
  • Are Drivers/Operators trained?
  • Are vehicles securely loaded?
  • Are reversing vehicles controlled?
  • Are vehicle warning signs displayed?
  • Does mobile plant have roll over protective structure?
  • Is protective structure in good repair?
  • Is seat belt effective and in good repair?
  • Has the propping been designed & inspected by a Competent Person?
  • Has falsework and formwork been checked by a Competent Person before pour?
  • Is there adequate bearing on all supports?
  • Are support frames/props plumb?
  • Are frames/props appropriately braced and/or tied?
  • Are the correct pins used in props?
  • Are forkheads used for bearer support?
  • Are forkheads wedged centrally?
  • Are screwjacks within maximum extension allowed?
  • Have falls from falsework and formwork been controlled?
  • Is machinery in good operating condition?
  • Are guards secured, operable & in good order?
  • Does machinery have current test certificate?
  • Do bench saws have a riving knife & hood guard
  • Does compressed air have matched & secured connections?