Bts access control commissioning checklist

Template Information

Access control commissioning certificate

Category: agriculture

Template Questions

  • Job Number
  • Site Name:
  • Site Address: Address
  • Door Controller Checks Secondary Voltage output
  • Door Controller Checks Voltage at PSU Primary
  • Door Controller Checks Current (mA) at PSU Secondary output
  • Check the installation, location and siting of the equipment and devices against the system record.
  • Carry out visual inspection of all major components:
  • Check all power supply voltages and charging rates at door controllers and lock PSU's inc mains voltages. Check battery condition and age.
  • Check operation of the reader and LED status for valid, invalid cards and reports.
  • Check operation of keypads if fitted i.e. valid and invalid pin numbers.
  • Check operation of door contacts ( if fitted ) correct indication of door forced and held open alarms
  • Check control equipment in accordance with company procedure.
  • Check the operation of any warning devices on the system.
  • Check operation of electronic release and ensure unrestricted operation of door closure. Visibly inspect equipment and tighten any loose fittings, Maglocks etc.
  • Check operation of egress button and emergency break glass operation.
  • Check operation of alarm inputs/outputs.
  • Check correct operation of PC Software and advise customer on backup of database where applicable.
  • Verify remote operation of lock release from PC including no access or blocking.
  • Check correct operation of ID badge and report printer ( if applicable ).
  • Check system is fully operational and carry out any minor adjustments
  • Resolve any customer questions and issues
  • Access Control -Checks
  • Photos of any Conditions actions named above
  • Enter Date and Time arrived on site: Date
  • Enter Date and Time finished on site: Date
  • Number of on-site hours:
  • Number of travel hours:
  • Engineers Name: for and On behalf of BTS Fire & Security
  • BTS engineers signature
  • Customers Acknowledgement (INPUT NAME): I confirm the satisfactory completion of the above maintenance visit.
  • Customer Job Title:
  • Customers Signature
  • Office use ONLY:
  • Actioned by:
  • Date Closed: